Time based work plan and achievement Up to December 2026

Project Name: Basic Infrastructure Development of ” Sheikh Hasina Institute of Frontier Technology (SHIFT)”

Division name: Information and Communication Technology Division,

Implementing Organization: Bangladesh Hi-Tech Park Authority

Source of funding: GOB

01
Master Plan Design

Work start date according to work plan: November 2022

Work end date according to work plan: June 2023

Status: Master Plan Design has been completed and Approved

 

02
Building Design

Work start date according to work plan: November 2022

Work end date according to work plan: June 2023

Status: Building Plan Design has been completed and Approved

 

03
Land Acquisition and Settlement

Work start date according to work plan: November 2022

Work end date according to work plan: September 2023

Status: Conducted research on Beneficiary. Partial Payment Released to DC office for Settlement.

 

04
SHIFT Law

Work start date according to work plan: February 2023

Work end date according to work plan: December 2023

Status: SHIFT Law is Waiting for Approval